Temporary Swing Space |
 |
| |
Challenge:
Aging public schools would require $80 million for the renovation and
modernization of facilities at nine school sites. The district’s
goal was to complete all school building construction without disruption to the education
process. Existing education facilities were at or above capacity. There was no additional
temporary swing space in the district to move students while construction was taking place.
The district’s architect and construction manager worked to determine
the best solution for students and staff. A plan was proposed that would
allow work to continue on a year round basis at all sites for periods
of 6 to 24 months each. A “trailer park” appearance was not
desirable and security was a concern.
Alternatives Reviewed: |
-
Renovate all buildings during the summer months
only — not feasible as the cost of the project would increase
due to inflation, multiple bids and construction mobilizations. “Traditional”
summer construction programs could take as long as 8 years (3 months
at a time) to complete.
-
Occupy available space in other buildings in town
- not feasible due to lack of available space.
-
Install 5 to 24 portable Classroom buildings per
site — not feasible due to limited space on school grounds and
30 - 40% increases in temporary construction costs to connect site
utilities and technology.
-
Install multiple 4 to 10 Classroom, temporary modular
complexes per site — the Innovative Modular Solution.
Solution:
Public bids were solicited and the District contracted with
Innovative Modular Solutions to provide Classrooms, labs, locker and office space
with 10 to 24 Classrooms per site. The 100,000 square foot modular construction
project was completed over the summer. Students occupied the building
in time for the Fall semester. |
-
Renovation of all the schools will occur without
disruption to the education process.
-
Students will remain on campus during construction
and have access to all facilities (gymnasium, library, cafeteria,
etc.). Only 4 to 6 Classroom entrances (vs. 10 to 24 needed for portables)
must be secured per site.
-
Two or three “school quality”, energy
efficient modular buildings were installed at each school.
-
All modular buildings will be occupied until construction
is complete. Each will be disassembled and returned to Innovative
Modular Solutions at the end of the construction program.
|
| |
We
would appreciate the opportunity to earn your business |
| |
 |
 |
 |
 |
A veteran teacher praised the
IMS modular buildings as
“the best Classroom I’ve ever had... As you can see, this
is nice. To me, it’s a good place to learn.”
(Detroit Free Press) |
 |
| |
 |
| |
Our
goal is to provide customer-focused, professional service
that will exceed your expectations. |
| |
297 E. South Frontage Rd, Unit B
Bolingbrook, IL 60440
Phone: 1-800-357-4699/1-630-972-0500
Fax: 1-630-972-0555 |
| |
| The information contained herein is proprietary
to Innovative Modular Solutions and may not be used, reproduced, or disseminated
without written consent. |